Shelton's 18-19 Construction Updates

18-19 Construction Updates

August 2019

Crews have been hard at work this summer wrapping up construction on Mountain View Elementary and Shelton High School.

Classrooms are complete and furnishings are starting to arrive at Mountain View Elementary. The gymnasium, offices, and kitchen will be completed in the next two weeks, and toward the end of August, staff will start moving in. Outside, the playgrounds are finished, and the exterior play shed weather cover is starting construction.

At Shelton High School, the new auxiliary gym, which will be called “Highclimber Gym”, is near completion with only a few minor items remaining. The new 3-story academic building is in the completion stages. Inside, admin offices and the 25 new classrooms are nearly finished. The new art studio, culinary arts kitchen, and science labs will be finished in the next few weeks. Outside, the parking lot and exterior walkways are steadily progressing.

Both schools are on track to welcome students for the first day of school, September 16th. Thank you, Shelton community, for your support!​


IMG_4261.jpg

Mt. View Elementary Near Completion



IMG_4255 (002).jpg

Shelton High School's New 3-Story Academic Building and Parking Lot Under Construction​

 


June 2019

Our construction crews have been hard at work and the bond projects are still on track for schools to be ready on the first day of school, September 16th! Shelton High School’s updated parking lot is well underway, and Mt. View Elementary is moving along smoothly. It is amazing the amount of work accomplished already, and so exciting to watch the progress!

Also great news...originally advertised, the construction bond was at $3.56 per 1000. The collection rate for 2019 is now $2.87 per 1000. That is $ .69 per 1000 less for our taxpayers!



65266003_384365692208311_959852163327066112_n.jpg
Shelton High School's parking lot update has begun.



65160180_400969837201717_2663198981324013568_n.jpg
Mt. View Elementary's former library and play shed being demolished. 


May 24, 2019

Mountain View Elementary​

Click here to see the progress: Bond Construction Progress - May 24, 2019​

Exterior:

Finishing up siding

Interior:

Started painting

Started casework and flooring

The elevator is currently being installed

What’s Next? This summer will bring a lot of exterior work of utilities, drives, walkways, playfields, etc.. Moving-in will begin mid-summer.

GOPR0186.JPG

Shelton High School

Exterior:

Finishing up the last window installs on the 3-story New Academic Building

Siding installation continues

Interior:

Mechanical/electrical/plumbing rough-in, insulation, drywall, and painting are occurring across the building

Auxiliary Gym:


Gym equipment has been installed

Bathrooms are being completed

GOPR0166.JPG


May 1, 2019

We are on the home-stretch of our bond projects! We are proud to say that our building projects are both on budget and on schedule to be ready for the first day of school, September 16th, 2019. With strikes and the weather causing a setback in construction, our crews have worked extremely hard to make up for the lost time. We want to thank everyone for their hard work on this project and each community member for your investment in our students and schools as we move towards the finish line.


Click here to see the progress: Bond Progress - May 2019
SHS.JPGMTV.JPG


March 2019

Early Learning Center Dedication

A beautiful late winter evening set the scene for those gathered at Shelton’s Early Learning Center dedication on March 5.

After many months of remodeling the Shelton Early Learning Center located at 403 K Street, is open to students. The update which included the facility being stripped down to the studs and the interior rebuilt now welcomes nearly 160 students each day. With seven classroom spaces, a new playground, and a new heating and cooling system, the youngest learners enjoy reaching new heights in preparation for their K-12 education.

Visitors to the center were welcomed by Superintendent Alex Apostle, Jenny LaFrenier, Director of Special Services, the Shelton School Board of Directors and Gail Straus, former Director of Early Childhood Education and Federal Programs, and community tours were guided by center staff.

The Early Learning Center now combines classes from both the Evergreen and Mt View Campuses into one coordinated facility where students learn community and classroom skills to prepare them for Kindergarten and beyond.

If you would like more information on our Early Learning Center or how your child can qualify, contact the Special Services Department in the Shelton School District.

We Are #SheltonProud​​​

IMG_1756.JPG IMG_1771.png

 


 


February 2019

​The snow storms in February that cancelled school for four days also delayed work on our bond projects. Work at Mt. View, though delayed, will not imact the overall transition schedule. The delays were longer at Shelton High School due to the roof not being complete before the snow came. The primary contractor is determining the effects on the construction schedule. At this time the buildins are all scheduled to open ontime in September 2019.


 

 

 


January 2019

 

Copy of Shelton SD Bond Budget_2018.12.11_summary.pdf

 

 

 

 

Bond Construction progress at Mt View Elementary, the Early Learning Center, and Shelton High school


November 30, 2018

Exciting progress is being made with our bond projects. Our buildings are taking shape and moving along in preparation for a September 16, 2019 opening.
Shelton High School is progressing vertically. The enormity of the structure is becoming visible. The steel is moving into place on the wing nearest the Performing Arts Center. Preparations are being made for the second and third floor decking then pouring the concrete floors. The remaining concrete floors on the main level have now been poured and in the coming weeks we will see the steel structure taking shape for the remainder of the building.

The Early Learning Center will welcome students in January 2019. The District Early Learning Center is on schedule for completion and will be turned over for district use in December. Teachers will moving their classrooms into this Early Learning space over Winter Break in preparation to welcome students back in January.

Mt. View Elementary continues to grow. The main classroom wing at Mt. View Elementary is now dried in, meaning the roof has been weatherized and is now water tight. This allows crews to move indoors to begin work on mechanical systems, rough plumbing and electrical work. This work will progress in the coming weeks and once completed the interior can begin to be completed. The remaining structure continues to grow and take shape. Be sure to check out our aerial videos for a birds eye view of the structure.

Aerial videos of our campuses under construction, more videos will be coming to allow you to follow construction progress.​


November 20, 2018

 
 





November 7, 2018

Walls are going up on the Auxiliary Gym
The Minidome is open for students and the community
Rough plumbing work is going in for the Shelton High School Addition and
Mt View Elementary has a roof over the main classroom wing!
All Buildings Will Receive Technology & Security Updates

Approved Bond Amount $ 64,778,906​

Package A - Shelton High School

Current Estimate $33,034,733
47,254 SF New Construction
19 Classrooms
4 Science Labs
1 Culinary Art Space
2 Art rooms
1 Yearbook/Photo Room
7049 SF Auxiliary Gym

Package B - Mt view Elementary

Current Estimate $26,960,070
54,995 SF New Construction
25 Classroom 2 Story Building
Early Learning Annex Remodel with Addition of 2 Portables
New Roof at Olympic Middle School

Package C - District Projects

Current Estimate $5,136,293
Nearing Completion
Boilers Replaced at Bordeaux
MCTC Parking Lot Repaved
1 New Portable + Improvements to Existing Portables at Evergreen
CHOICE High School New Roof and Cooling Tower
Derelict Maintenance Buildings Demolished
Covered Walkways and Bordeaux and Evergreen Installed​

Construction at Shelton High School. footings for the new building and walls being framed at the auxiliary gymGrade Configuration Beginning September 2019

Elementary Schools
Grades K-4

Olympic Middle School
Grades 5-6

Oakland Bay Jr High
Grades 7-8

Shelton High School
Grades 9-12​


October 2018​

NAC Architecture attended the October 11 Community Forum at Olympic Middle School where they presented the latest 3-D Overview of our project at Shelton High School. In attendance also was Jeff Freeney from KMB Architects who is overseeing all the projects in Shelton. The Bond update slides can be found below. The entire community forum was Live Streamed on Facebook​ and can be watched in its entirety.


KMB Architect Slides

 

 

 

NAC Architecture Overview of Shelton High School

 





Shelton High School has recently seen concrete going in for the footings and foundation in the new building as well as work progressing on the Student Services in Building 100. New paint is also being applied to the existing buildings bringing a bright new look to our 45 year old buildings. The Second Story of Mt View Elementary is also taking shape.

The Playground for the Early Learning Center was recently completed allowing our smallest students to enjoy time outdoors.

Shelton High School has recently seen concrete going in for the footings and foundation in the new building as well as work prog


October 9, 2018 


 
 
 


September 2018

We were out and about today and took some pictures for you of our Bond Project progress.

*Mt View is preparing for the second floor on the main classroom wing.
*Olympic Middle School is getting a new roof
*Shelton High School is seeing progress with the rebar going in for the Auxiliary Gym, and the main building footings are being prepared for concrete.

On Friday Shelton High School will reach a major milestone with waterline to the new building will be pressurized after school is released. This step must be completed before concrete footings and foundation work can be completed. Water will be shut off to the entire campus during this process.

It is exciting to see our projects taking shape.

We Are #SheltonProud
#sheltonbondprojects

Mt View Elementary building construction Olympic Middle School Roof replacement

Shleton High school Footing and foundation trench Shelton High School Auxiliary Gym floor before concrete is poured


KMB Architect Slides

 

 

 

NAC Architecture Overview of Shelton High School

 

KMB Architect Slides

 

 

 

NAC Architecture Overview of Shelton High School

 
 
  • 700 S. First St., Shelton, WA 98584
  • p: 360-426-1687
  • f: 360-427-8610

The Shelton School District does not discriminate in any programs or activities on the basis of sex, race, creed, religion, color, national origin, age, veteran or military status, sexual orientation, gender expression or identity, disability, or the use of a trained dog guide or service animal and provides equal access to the Boy Scouts and other designated youth groups. The following employee has been designated to handle questions and complaints of alleged discrimination: Linda Arnold, Director of Human Resources. 360-426-1687. 700 S. 1st Street; Shelton, WA 98584. Complaint procedure can be found on this website under Board Policy #3210 (students) and #5010 (employees).